Eskom granted approval to run Koeberg Unit 1 until 2044.

By Lehlohonolo Lehana.

State owned power utillity Eskom’s Koeberg nuclear power plant will be allowed to run one of its two units for another 20 years, the country’s nuclear regulator NNR said on Monday. 

The decision came only days ahead of the July 21, 2024 expiry of Unit 1’s existing licence and effectively extended its operating life until July 21, 2044.

The licence variation is expected to be issued soon and allows for the “seamless” operation of Unit 1, as no conditions were included requiring Eskom to proceed with a shutdown that had initially been scheduled to begin on July 21.

In January, the NNR also confirmed that it had agreed to Eskom’s request to separate the Unit 1 and 2 licences to align with their respective commercial operating dates, with Unit 1 having started operating in July 1984 and Unit 2 in November 1985.

For this reason, Unit 2’s existing licence will remain in place until November 9, 2025, providing the NNR board with additional time to make an assessment on the life extension of the second reactor.

Unit 2 is currently undergoing an extended shutdown that includes the replacement of its three steam generators, a key requirement for any long-term extension of the reactor’s operating life.

NNR CEO Ditebogo Kgomo said the board had made the decision to approve Unit 1’s life extension in line with governing legislation, international safety standards and following a public participation process, which included eight public hearings.

Eskom had applied for the extension on May 10, 2021, together with a request for a separation of the Unit 1 and 2 licences to enable the ongoing operation of Unit 2 beyond July 21, 2024.

The decoupling of the licences was granted by NNR on January 25 this year.

“With regards to the representations received during public consultations, we found that the substantive concerns raised on health, safety and environment were adequately addressed by the licence conditions and/or the safety case, “Kgomo said.

She said the installation of a core catcher was not a requirement of the Unit 1 licence extension and argued that it was also not the case for other second-generation reactor extensions globally. This, despite indications that it is indeed a requirement for the life extension of such reactors in France.

Kgomo added that the NNR’s technical review concluded that Eskom’s Long Term Operation (LTO) application was compliant with LTO regulations concerning the following: the submission of the safety case for long-term operation; factors related to safety-related programmes; effectiveness of the aging-management programme; the utilisation of the periodic safety review; and the programme for long-term operations with respect to the revalidation of time-limiting aging analysis.

“The NNR review found that the application is compliant for Unit 1,” Kgomo said, adding that the review of some aspects of the revalidation of time-limiting aging analysis on Unit 2 was ongoing.

Scroll to Top