Eskom implement stage 2 load shedding – Here are three worst-performing plants.

By Lehlohonolo Lehana.

Power utility Eskom has announced that stage 2 load shedding will be introduced on Monday evening due to a further breakdown of units.

“Eskom regrets to inform the public that, due to the breakdown of a generation unit each at Majuba and Medupi power stations today, Stage 2 load shedding will be implemented from 17h00 until 22h00 tonight. Three generation units are expected to return to service by this evening, which will ramp up through the night.”

The power utility said it will continue to closely monitor the system, and adjust and communicate any changes as may be necessary.

“We appeal to all South Africans to help limit the impact of the shortages by continuing to reduce the usage of electricity and to switch off all non-essential items. We currently have 2,246MW on planned maintenance, while another 15,847MW of capacity is unavailable due to breakdowns.

“Eskom cautions the public that as the shortage of generation capacity persists, the system will continue to be constrained with an elevated risk of load shedding over the coming weeks.”

Eskom noted that load shedding is implemented only as a last resort to protect the national grid. “We, therefore, urge all South Africans to continue using electricity sparingly especially between 05h00 – 09h00 in the mornings and 16h00 – 22h00 in the evenings.”

For people living in the major metros, load shedding schedules are available here:

For access to other load shedding schedules, Eskom has made them available on loadshedding.eskom.co.za.

Smartphone users can also download the app EskomSePush to receive push notifications when load shedding is implemented, as well as the times the area you are in will be off.

Eskom’s three worst-performing plants

Tutuka, Kendal and Duvha – accounted for 44%, or nearly half, of all Eskom plant breakdowns in the 12 months to March.

This emerged at the utility’s state of the system briefing earlier this month. On average, Tutuka had 2 256 megawatts (MW) of generation capacity unavailable for the most recent financial year which ended in March. Kendal had an average of 1 613MW of generation offline, while Duvha had 1 139MW unavailable.

Together, this totals 5 008MW. If Eskom was to fix these clearly broken power stations – likely both from an engineering (plant) and human resources point of view – and restore just half of these amounts offline, this would be enough to plug the shortfall that Eskom currently has during the evening peak.

Eskom confirmed to Moneyweb that the main contributors to outages across the fleet – boiler (20%), turbine (17%), draught plant (14%) and generator (10%) – were consistent at these three worst-performing plants. It says “in addition, outage slips and trips were also significant contributors at Tutuka”.

Troubled Tutuka

Tutuka near Standerton, with nominal capacity of 3 510MW, is Eskom’s worst-performing power station by some margin.

That an average of 2 256MW of generation was offline due to breakdowns – referred to as unplanned capability loss factor (UCLF) – means only a third of the station (two of its six units) was online, on average, during the 2021/22 financial year. This figure excludes any planned maintenance.

In the first, a cable to unit five was severed which delayed its return to service. This was discovered the same day that “the control air pipe supplying the turbine systems had been cut with a power tool and the entire bend removed”.

It was reported that the latter was done just outside of the view of CCTV cameras. The acts were reported to police.

In a statement, Eskom said it believed “these were deliberate acts of sabotage by someone who had access to the site where only employees have access and knows the security features in the area quite well”.

Last August, Eskom suspended seven managers at Tutuka. In the last financial year, it reportedly suspended 20 employees on matters related to “theft and collusion” after the apparent theft of R1.3 billion in spares from the power station during the year.

Kendal and Duvha

At Kendal, near Emalahleni, nominal capacity is 3 840MW (from installed capacity of 4 116MW). The 1 613MW of “average” generation capacity lost to breakdowns equates to around 42%.

The number at Duvha, also to the south of Emalahleni, is similar. It has nominal capacity of 2 875MW and the capacity offline for unplanned reasons averaged 39% for the last financial year.

Duvha has already permanently lost 575MW of capacity. Duvha Unit 3, which exploded in 2014, was originally meant to be replaced. Eskom forecast this to be “recovered” in 2019/20. The utility received an insurance payout of R4.2 billion for the incident in 2015. The recovery project was cancelled in around 2018.

The return-to-service date for Unit 2 at Duvha – which was already six months overdue, apparently due to several ‘mistakes’ that kept delaying progress on restarting the unit – was delayed further earlier this month when it was discovered that the incorrect oil had been used.

The top performers

By comparison, at Eskom’s two best-performing large coal-fired power stations – Lethabo (3 558MW of nominal capacity) and Matimba (3 690MW of nominal capacity) – the average amount of generation offline due to unexpected breakdowns equates to 10% and 13% of capacity respectively.

This is very close to Koeberg’s average unplanned losses, which equated to 9.6% in the most recent financial year.

Eskom has previously said the recent suspicious incidents (at Tutuka and Duvha, as well as another at Hendrina) are the difference between it having enough generation capacity and being forced to implement load shedding.